DFARS 209.570-4 — Solicitation provision and contract clause
Regulatory text. Not legal advice.
(a)
(a) Use the provision at DFARS 252.209-7006, Limitations on Contractors Acting as Lead System Integrators, in solicitations for the acquisition of a major system when the acquisition strategy envisions the use of a lead system integrator.
(b)
(b) Use the clause at DFARS 252.209-7007, Prohibited Financial Interests for Lead System Integrators—
(1) In solicitations that include the provision at DFARS 252.209-7006; and
(2) In contracts when the contractor will fill the role of a lead system integrator for the acquisition of a major system.
Source: eCFR • Pulled 2026-04-16