FAR 11.500 — Scope
Regulatory text. Not legal advice.
(a)
(a) This subpart prescribes policies and procedures for using liquidated damages clauses in solicitations and contracts for supplies, services, research and development, and construction.
(b)
(b) This subpart does not apply to liquidated damages—
(1) For subcontracting plans (see FAR 19.705-7);
(2) Related to the Contract Work Hours and Safety Standards statute (see FAR Subpart 22.3); or
(3) Related to paid sick leave for Federal contractors (see FAR Subpart 22.21).