FAR 16.402-3 — Delivery incentives
Regulatory text. Not legal advice.
(a)
(a) Delivery incentives should be considered when improvement from a required delivery schedule is a significant Government objective. It is important to determine the Government’s primary objectives in a given contract (e.g., earliest possible delivery or earliest quantity production).
(b)
(b) Incentive arrangements on delivery should specify the application of the reward-penalty structure in the event of Government-caused delays or other delays beyond the control, and without the fault or negligence, of the contractor or subcontractor.