(a)

(a) Insert the following clauses in solicitations and contracts in excess of $2,000 for construction within the United States:

(1) FAR 52.222-6, Construction Wage Rate Requirements.

(2) FAR 52.222-7, Withholding of Funds.

(3) FAR 52.222-8, Payrolls and Basic Records.

(4) FAR 52.222-9, Apprentices and Trainees.

(5) FAR 52.222-10, Compliance with Copeland Act Requirements.

(6) FAR 52.222-11, Subcontracts (Labor Standards).

(7) FAR 52.222-12, Contract Termination—Debarment.

(8) FAR 52.222-13, Compliance with Construction Wage Rate Requirements and Related Regulations.

(9) FAR 52.222-14, Disputes Concerning Labor Standards.

(10) FAR 52.222-15, Certification of Eligibility.

(b)

(b) Insert the clause at FAR 52.222-16, Approval of Wage Rates, in solicitations and contracts in excess of $2,000 for cost-reimbursement construction to be performed within the United States, except for contracts with a State or political subdivision thereof.

(c)

(c) A contract that is not primarily for construction may contain a requirement for some construction work to be performed in the United States. If under FAR 22.402(b) the requirements of this subpart apply to the construction work, insert in such solicitations and contracts the applicable construction labor standards clauses required in this section and identify the item or items of construction work to which the clauses apply.

(d)

(d) [Reserved]

(e)

(e) Insert the clause at FAR 52.222-30, Construction Wage Rate Requirements—Price Adjustment (None or Separately Specified Pricing Method), in solicitations and contracts if the contract is expected to be—

(1) A fixed-price contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract, and the contracting officer determines the most appropriate contract price adjustment method is the method at FAR 22.404-12(c)(1) or (2); or

(2) A cost-reimbursable type contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract.

(f)

(f) Insert the clause at FAR 52.222-31, Construction Wage Rate Requirements—Price Adjustment (Percentage Method), in solicitations and contracts if the contract is expected to be a fixed-price contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract, and the contracting officer determines the most appropriate contract price adjustment method is the method at FAR 22.404-12(c)(3).

(g)

(g) Insert the clause at FAR 52.222-32, Construction Wage Rate Requirements—Price Adjustment (Actual Method), in solicitations and contracts if the contract is expected to be a fixed-price contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract, and the contracting officer determines the most appropriate method to establish contract price is the method at FAR 22.404-12(c)(4).

(h)

(h) Insert the provision at FAR 52.222-5, Construction Wage Rate Requirements—Secondary Site of the Work, in solicitations in excess of $2,000 for construction within the United States.


Citation history: [53 FR 4935, Feb. 18, 1988, as amended at 66 FR 53481, Oct. 22, 2001; 70 FR 33667, June 8, 2005; 72 FR 27384, May 15, 2007; 79 FR 24205, Apr. 29, 2014]