FAR 36.204 — Disclosure of the magnitude of construction projects
Regulatory text. Not legal advice.
Advance notices and solicitations shall state the magnitude of the requirement in terms of physical characteristics and estimated price range. In no event shall the statement of magnitude disclose the Government’s estimate. Therefore, the estimated price should be described in terms of one of the following price ranges:
(a)
(a) Less than $25,000.
(b)
(b) Between 100,000.
(c)
(c) Between 250,000.
(d)
(d) Between 500,000.
(e)
(e) Between 1,000,000.
(f)
(f) Between 5,000,000.
(g)
(g) Between 10,000,000.
(h)
(h) More than $10,000,000.