FAR 36.502 — Differing site conditions
Regulatory text. Not legal advice.
The contracting officer shall insert the clause at FAR 52.236-2, Differing Site Conditions, in solicitations and contracts when a fixed-price construction contract or a fixed-price dismantling, demolition, or removal of improvements contract is contemplated and the contract amount is expected to exceed the simplified acquisition threshold. The contracting officer may insert the clause in solicitations and contracts when a fixed-price construction or a fixed-price contract for dismantling, demolition, or removal of improvements is contemplated and the contract amount is expected to be at or below the simplified acquisition threshold.
Citation history: [48 FR 42356, Sept. 19, 1983, as amended at 60 FR 34759, July 3, 1995]
Source: eCFR • Pulled 2026-04-16