FAR 8.403 — Applicability
Regulatory text. Not legal advice.
(a)
(a) Procedures in this subpart apply to—
(1) Individual orders for supplies or services placed against Federal Supply Schedules contracts; and
(2) BPAs established against Federal Supply Schedule contracts.
(b)
(b) GSA may establish special ordering procedures for a particular schedule. In this case, that schedule will specify those special ordering procedures. Unless otherwise noted, special ordering procedures established for a Federal Supply Schedule take precedence over the procedures in FAR 8.405.
(c)
(c) In accordance with section 1427(b) of Public Law 108-136 (40 U.S.C. 1103 note), for requirements that substantially or to a dominant extent specify performance of architect-engineer services (as defined in FAR 2.101), agencies—
(1) Shall use the procedures at FAR Subpart 36.6; and
(2) Shall not place orders for such requirements under a Federal Supply Schedule.
Citation history: [69 FR 34234, June 18, 2004, as amended at 70 FR 11738, Mar. 9, 2005; 79 FR 24199. Apr. 29, 2014]
Source: eCFR • Pulled 2026-04-16